The Armstrong Siddeley Energy Centre Project

The Armstrong Siddeley Energy Centre

 

The Envirotech Group are delighted to have completed The Armstrong Siddeley Energy Centre for Coventry University, which was no small task! Our staff have worked tremendously installing:

  • 5Mw Gas Boilers
  • 140kW Bosch CHP
  • 10,000l external thermal stores
  • 500kW Chiller
  • 25 Week Programme
  • 12,500 accident-free site hours
  • On Budget & Ahead of Programme.

 

The Armstrong Siddeley Energy Centre

An insight into some project details

Envirotech were appointed as the main contractor to provide a turnkey solution. The project was completed over a 25 – week programme to coordinate with the university summer break, with a critical ‘heat on’ date to ensure zero disruption.

The scope included a full strip out & installation of 3 boilers, 1 new chiller, 1 CHP, all associated pipework, pumps & controls. The new Energy Centre feeds district-heating circuits to several campus buildings.

A temporary heating plant was provided from April—July & Temporary DHWS plant from July —September & all DHWS services were kept live.

The existing boosted cold water provision was replaced with a packaged booster ‘room’.

A new chilled water pumping room was created externally within a new GRP enclosure.

Thermal stores were located externally and suitably weather treated.

The system was switched from an open vented to a sealed system, & existing MCWS tanks were removed & the domestic water systems pressurized.

 

The Armstrong Siddeley Energy Centre

 

Project constraints

A live ‘college environment’ with operational hours 7am – 10pm, 7 days per week meant that ‘out of hours’ shutdowns were very limited, from midnight for a 6 hour maximum period!

Restricted site access required diligent planning & regular stakeholder meetings to ensure zero disruption to campus operations.

There was a requirement to work very close to existing landscaping with TPO’s, Envirotech worked closely with the university grounds team to develop a tree-root protection plan & avoid damage.

Commendation from Lee Hatton at Coventry University:

“Thank you to the entire Envirotech Group for all the hard work in completing The Energy Centre. Our first ever early completion!”