Aston Manor Academy

Aston Manor Academy

Sector: Industrial

Work elements: Mechanical and electrical

Period of works: July 2014 – Sept 2014

Total time span: 11 weeks

Project value: £160k

Overview: To strip out the old boiler plant, pumps, feed and expansion tanks and install new boilers, pressurisation set, buffer vessels and associated plants including pumps, pipe work, flues, electrical services and BMS control.

 

  • Category: Industrial
  • Client: Aston Manor Academy
  • Date: July 2014 - Sept 2014
  • Website: