Aston Manor Academy, Birmingham

Download as PDF
Work Elements:
Mechanical and electrical
Period of Works:
July 2014 – Sept 2014
Total Time Span:
11 weeks
Project Value:
£160k
Overview:

Strip out the old boiler plant, pumps, feed & expansion tanks and Install new boilers, pressurisation set, buffer vessels and associated plants including pumps, pipe work, flues, electrical services & BMS control.

Coventry University - Charles Ward Energy Centre

Download as PDF
Work Elements:
New 6.5mw energy centre
Period of Works:
June 2014 - September 2014
Total Time Span:
12 weeks including 5 week asbestos strip out
Project Value:
£2.2m
Overview:
  • 6.5mw of Heating load
  • Thermal store 34,000 litre
  • BIM model
  • NEW CHP
  • Revitt Modelling
  • Saving of 489 tonnes of carbon
  • off site fabrication
  • Temporary boiler plant for hot water
  • 5 new 1200kw boilers
  • New flue system
  • Siemens Bons control
  • 350kw air cooled chiller
  • "spill & fill" pressurisation units
  • Ongoing water

Howdens Joinery, Goole

Download as PDF
Work Elements:
4 new biomas boilers 1100kw. 4 new 1100kw gas fired boiler control systems
Period of Works:
October 2013 - February 2014
Total Time Span:
5 months
Project Value:
£2.25m
Overview:

Design, install test, witness test, commission, demonstrate.

Two temporary boilers to maintain ambient heat for the working factory during our install.

Green Energy Immingham Docks

Download as PDF
Work Elements:
Two new 1500kw steam boilers including controls. Two new 600kw chillers.
Period of Works:
January 2014 - May 2014
Total Time Span:
5 Months
Project Value:
£1.688m
Overview:
  • Install new steam boilers to provide 250mm steam line for the process plant to produce bio-fuels. To supply 15kgs / hour @ 15 bar.
  • Install two new 600kw chillers for the end process.
  • controls associated pipe work, plant controls and insulation

Wood Norton Hotel

Download as PDF
Work Elements:
Mechanical, electrical and air conditioning
Period of Works:
July - October 2012
Total Time Span:
16 weeks
Project Value:
£949k
Overview:

Refurbishment of 16th century historic hotel, associated buildings new bedroom block and conference centre, including new electrical, plumbing, heating, ventilation and air conditioning installations. Sympathetically install 38No Mitsubishi electric VRF units throughout the hotel, which were generally within public areas, the floor mounted chassis units; are installed within bespoke cabinets, with the services to each unit being installed, through the cellars and beneath the floors for concealment. On the first floor, the ducted fan coil units, are concealed within divan beds with all services hidden within the building fabric. On the Second floor, the units are ducted FCU's installed in the loft space.